As soon as tomorrow (Thursday, April 4, 2024), New England could have a new long-term transmission planning process—and one that puts the states in the driver’s seat.
The New England Power Pool (“NEPOOL”) Transmission Committee voted on March 27 to approve a proposal, crafted jointly by ISO New England (“ISO-NE”) and the New England States Committee on Electricity (“NESCOE”), to establish procedures for states to direct the ISO to solicit transmission solutions, including those needed to meet states’ energy policy goals. The “Extended-Term/Longer-Term Transmission Planning Phase 2” proposal, “Phase 2” for short, follows on the heels of a “Phase 1” process that was approved by the Federal Energy Regulatory Commission (“FERC”) in 2022. Phase 1 provides a roadmap for NESCOE to require that the ISO perform system planning analyses, including analyses that anticipate needs beyond a ten-year planning horizon. Phase 2 enables NESCOE to require that the ISO conduct solicitations to fulfill the transmission needs identified in Phase 1. After last week’s decision by the Transmission Committee, the Phase 2 proposal needs to survive one more vote (by the NEPOOL Participants Committee) this coming Thursday before it is eligible to go up to FERC for approval.
The two phases, taken together, constitute a novel innovation in large-scale transmission planning that we’ve not yet seen outside of single-state ISOs: the handing-off of meaningful control over decisions to study and address transmission needs to state policymakers. The new process will enable NESCOE to determine—and direct the construction of—transmission infrastructure necessary to meet their respective states’ energy policy goals or legal mandates around emissions reductions. By default, the costs of such projects will be regionalized where they are commensurate with project benefits; where such an allocation is insufficient to cover costs, individual states can pay the balance so that a project can proceed.
Notably, the March 27 vote saw the Transmission Committee approve an amendment requiring ISO-NE to conduct independent cost assessments of bids submitted by transmission developers. While bidders will still use their own methodologies to calculate project costs, the ISO will then re-estimate the costs of each project using a consistent methodology.
If approved by the NEPOOL Participants Committee, the proposed changes will take effect in August 2024.
We use cookies to enhance user experience, improve functionality and performance, and for analysis of website traffic. By clicking “accept”, you agree to the use of cookies. For more information about our cookie policy and the information we collect, please review our Privacy Statement.
Foley Hoag
Email Disclaimer
Transmitting information to us by e-mail unilaterally does not establish an attorney-client relationship or impose an obligation on either the law firm or even the receiving lawyer to keep the transmitted information confidential. By clicking "OK," you acknowledge that we have no obligation to maintain the confidentiality of any information you submit to us unless we already represent you or unless we have agreed to receive limited confidential material/information from you as a prospective client. Thus, if you are not a client or someone we have agreed to consider as a prospective client, information you submit to us by e-mail may be disclosed to others or used against you.
If you would like to discuss becoming a client, please contact one of our attorneys to arrange for a meeting or telephone conference. If you wish to disclose confidential information to a lawyer in the firm before an attorney-client relationship is established, the protections that the law firm will provide to such information from a prospective client should be discussed before such information is submitted. Thank you for your interest in Foley Hoag.